Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

BC launches 22 new primary care networks, including one in Mission

Will be adding family physicians, a nurse practitioner and a social worker

Mission Mayor Pam Alexis to run for the NDP

Will take on Liberal Simon Gibson in the Abbotsford-Mission riding

MEDICAL MOMENTS: Dr. Andrew Edelson has served Mission for more than 45 years

Why Mission? ‘Mostly because it’s such a wonderful community,’ he says

Unofficial holidays: Here’s what people are celebrating for the week of Sept. 27 to Oct. 3

World Farm Animals Day, Drink Beer Day and Virus Appreciation Day are all coming up this week

Missing Chilliwack woman last seen on Wednesday

Friends and family concerned for Joy-Lynn Leon, 42, who was last seen Sept. 23 on Mary Street

QUIZ: Do you know what’s on TV?

Fall is normally the time when new television shows are released

Horgan, Wilkinson trade barbs over MSP premiums, health care at campaign stops

Horgan called a snap election for Oct. 24 earlier this week

VIDEO: COVID won’t dampen Lower Mainland woman’s Halloween spirit

Langley’s Tanya Reid posted video offering suggestions of how trick-or-treating might look for her

2 British Columbians arrested, 3 at large in massive Alberta drug bust

Eight people are facing 33 charges in what police have dubbed Project Incumbent

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

97 distressed horses, cats and dogs seized from farm in Princeton

RCMP assisted as BC SPCA executed search warrant

Father hopes journey to aviation-safety program inspires hope

Former South Surrey resident Greg Sewell hasn’t given up on quest to mandate older-plane retrofits

$250K reward offered as investigation continues into Sea to Sky Gondola vandalism

Police also asking for specific footage of Sea to Sky highway around time of incident

Most Read