Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Signs at a new COVID-19 testing and collection centre at 14577 66th Ave. in Surrey. It was relocated from an urgent primary care centre near Surrey Memorial Hospital. This new centre allows for up to 800 tests per day, which is 550 more than the previous centre, according to Fraser Health. (Photo: Lauren Collins)
More than 200 new COVID-19 cases linked to Fraser Health region: Dr. Henry

Provincial health officer appeals to people to keep gatherings small

Currently, many bike enthusiasts use the Mission skate park, but council has now decided to create a pump track for the community. / File Photo
Mission council approves $300,000 for recreational biking pump track

Bike skills park at Mission Leisure Centre to be considered in 2021 budget

The Rapid Rectangular Flashing Beacon installed on Stave Lake Street and Best Avenue, which will be operational in the next several weeks. District of Mission photo.
New type of pedestrian-crossing light coming to Mission

Rapid Rectangular Flashing Beacon installed on Stave Lake Street and Best Avenue

Photo courtesy of Mission RCMP.
MISSING: Mission RCMP request assistance in search for Joseph Pierce

Pierce last seen in Abbotsford on Oct. 6, may be headed to Alberta

fdf
Massive new six-building complex planned for development in Mission

Complex would bring 289 residential units, 11 commercial retail units and four new office spaces

Vancouver police reactivated the search for Jordan Naterer Thursday Oct. 22. Photo courtesy of VPD.
Mom of missing Manning Park hiker believes her son is waiting to come home

‘He’s going to come out of a helicopter and say ‘what took you so long?”

Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce that B.C. Hydro is proceeding with construction of the Site C dam, Dec. 11, 2017. (Tom Fletcher/Black Press)
Site C actions, costs won’t be known until after B.C. election, Horgan says

Peace River diverted for construction of reinforced dam base

One of the squirrels who ended up having their tails amputated after getting them stuck together with tree sap. (Facebook/Wild ARC)
Squirrels recovering from tail amputation after sap situation near Victoria

BC SPCA Wild ARC says squirrels will be released back into wild, fifth sibling was euthanized

More and more electric cars are on the road, but one Chevy Bolt owner was shocked to see how much his BC Hydro bill skyrocketed once he started charging the vehicle. (Black Press file photo)
Lower Mainland man sees significant spike in BC Hydro bill after buying electrical vehicle

An increase should be expected, but Brian Chwiendacz experienced a 200-plus per cent hike

The Anonymous YVR is an Instagram page that reviews restaurants and other establishments around B.C. based on how well they adhere to COVID-19 rules. (Instagram)
Anonymous Instagram page reviews COVID-19 safety measures at B.C. businesses

There are a number of public health orders various types of establishments must follow to slow virus’s spread

The Vancouver Canucks and Abbotsford’s Jake Virtanen have agreed to a two-year deal with an average annual salary of $2.55 million. (@Canucks Twitter photo)
Abbotsford’s Jake Virtanen, Vancouver Canucks agree to two-year deal

Two sides avoid arbitration, Virtanen will receive average annual salary of $2.55 million

Most Read