Clark warns of $600 million delay to Site C dam

NDP leader John Horgan says Clark’s claims ‘unsupported’

Premier Christy Clark has written to the NDP and Green Party leaders, warning that a delay in removing two homes from the path of a Site C dam road could delay the project by a year and cost as much as $600 million.

In letters released Tuesday, Clark asked both NDP leader John Horgan and B.C. Green Party leader Andrew Weaver to reconsider Horgan’s request to delay the removal of two homes on land expropriated by BC Hydro for the third dam on the Peace River.

A decision must be made by June 15 on whether to proceed, Clark wrote. Her letters also ask:

“…whether or not you would like government to issue a ‘tools down’ request to BC Hydro on the other decisions that are essential in maintaining the budget and construction schedule of the Site C Clean Energy Project, given that the project is likely to progress past the ‘point of no return’ before the B.C. Utilities Commission review you have suggested could be reasonably concluded.”

Horgan responded Tuesday, calling Clark’s claims of cost escalation “unsupported” and accusing the B.C. Liberals of driving up BC Hydro bills due to “mismanagement” of the project.

Weaver also responded to Clark’s letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.

Horgan wrote to BC Hydro CEO Jessica McDonald May 31 to ask for a lease extension for two families, including Peace Valley Landowner Association members Ken and Arlene Boon, whose homes are on a road right-of-way needed for the dam.

“I believe there is no demonstrated short-term need to force these families from their homes, and because the status of the next governments of British Columbia are uncertain, the threat of imminent removal of residents from their expropriated homes and property is unreasonable,” Horgan wrote.

Clark’s letter says “the relocation of the homes in question is necessary as part of a two-year road and bridge construction project that will enable river diversion to occur in September 2019.”

River diversion has to be done when water is low in summer, not in winter when the two existing Peace River dams are running water through turbines to supply winter electricity demand.

“Preliminary work undertaken on this issue by BC Hydro indicates that should river diversion not be completed as scheduled, a year-long delay would occur in order to divert the river during the next low-flow period, in September 2020,” Clark wrote. “This one-year delay is estimated to cost ratepayers $600 million.”

“Given the obligation that BC Hydro has in place with respect to road construction and completion, a decision to proceed will need to be made no later than June 15, 2017 in order to maintain the September 2019 river diversion schedule.”

Weaver responded to Clark’s letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.

Just Posted

Crown appeals stay against Jamie Bacon in Surrey Six killings

B.C.’s prosecution service says judge’s decision reveals ‘errors of law’

Mission recycling numbers improving

Less recyclable material being tossed in trash

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

Abbotsford and Mission consider Fraser River water source

Project cheaper than Stave Lake but could still cost more than $50 million

FVRD fire dispatch services to move from Chilliwack to Vancouver

Six part-time jobs eliminated; employees told of the decision two weeks before Christmas

VIDEO: Mission Friendship Centre Christmas Market

Christmas Market comes to Mission

Liberal Hogg wins South Surrey-White Rock byelection over Conservative Findlay

B.C. riding to be represented by non-conservative for first time in decades

Six-year-old boy needs $19,000 a month to treat rare form of arthritis

Mother of sick Sooke boy asks government to help fund treatments

Environmental groups slam NDP decision to continue with Site C

Construction industry, meanwhile, is cautiously optimistic about how the project will look

Be ladder safe both at work and home

WorkSafeBC wants you to keep safe while hanging those Christmas lights this year

Cold weather shelter too full, buses homeless to other communities

The Gateway of Hope shelter has had send some people to other shelters as they ran out of room.

B.C. overdose deaths surpass 1,200

96 people died of illicit drug overdoses in October

Mission Secondary show sold out

The school’s presentation of A Christmas Carol runs for three days

Feds agree to give provinces 75 per cent of pot tax revenues

Finance Minister Bill Morneau announced the agreement today

Most Read